I worked for a company who built power stations, not little things, massive ones powering the National Grid.
“Richard, we have a problem in Warwickshire. One of the generators keeps cutting out. Every morning. 850 Megawatts. Go and find out what’s happening.”
So there I was early next morning.
I sat and watched. No problem.
Day two. I watched as a cleaner went along dusting the gauges.
‘Bang’. Sirens going, red lights flashing. The generator stopped. 850 megawatts down.
So simple! One of the gauges had a cutout on it.
Static from the cleaner’s cloth had activated it.
Job solved.
Richard Hunt 10 months ago
This is all true.
Christopher 10 months ago
Wow. That's pretty cool.
Neville Hunt 10 months ago
Well done Richard... I never knew😕
Richard Hunt 10 months ago
Well it was an interesting job and, as a result I became the Mr Fixit of the department. This was when I worked in Manchester, of course … which was where we boiled the canal - No 1 of the series. At least 2 more to come … both very different.
Neville Hunt 10 months ago
Look forward to reading them! Things I never knew about my bruv!